TEARDOWN Published 24 November 2026 at 03:58. Evidence-based. Source-cited. No sponsored content.

Ministers call their new prison part of the 'largest prison building boom since the Victorian era.' It is the unbuilt remainder of a 2021 pledge whose cost has nearly doubled, their own strategy admits.

4 out of 5 stars4/52 documented mistakes in this teardownHow ratings work

Estimated reading time: 6 minutes

The entrance gatehouse of HM Prison Leicester, a Victorian-era prison building with a stone archway.
HM Prison Leicester, a prison built in the Victorian era, photographed 15 November 2009. Photo: NotFromUtrecht / Wikimedia Commons, CC BY-SA 3.0.

In short. On 13 November 2026 the Ministry of Justice marked a construction milestone at HMP Welland Oaks in Leicestershire by calling the programme "the largest prison building boom since the Victorian era", crediting the government with delivering "14,000 additional places by 2031" [1]. The department's own 10-Year Prison Capacity Strategy, published December 2024, says those 14,000 places are "the 14,000 prison places the last Government promised", the unbuilt remainder of a 20,000-place pledge made in October 2021 [2]. The same document shows the cost of that programme has risen from an estimated 5.2 billion pounds in 2021 to between 9.4 billion and 10.1 billion now, and the National Audit Office, reporting the same month, found the underlying expansion plan "unrealistic and was not prioritised by the government" [3]. The department's own newest capacity statement, from January 2026, says supply only keeps pace with demand once Sentencing Act 2026 early releases are added in, and that the Ministry has acquired no new prison land in over 10 years [4]. Two documented mistakes: four stars.

On 13 November 2026, workers lifted the final steel beam into place at HMP Welland Oaks, a new category B prison for men being built in Market Harborough, Leicestershire. The Ministry of Justice marked the moment with a press release describing the site as part of "the largest prison building boom since the Victorian era, as the Government delivers 14,000 additional places by 2031, after just 500 net places were added in the 14 years to July 2024" [1]. The Minister for Prisons, Catherine McKinnell, said the government had "already delivered 3,300 places across the country and are investing billions to build thousands more" [1].

What the release does not say is where the 14,000 figure comes from, or what reaching it has cost.

A pledge, not a new ambition

In October 2021, the previous government promised 20,000 new prison places by the mid-2020s [3]. By the time it left office in July 2024, it had "built just 6,000 of them", according to the current government's own account [2]. The 10-Year Prison Capacity Strategy, published in December 2024, is explicit about what the remaining figure represents: "It sets out how this Government will build the 14,000 prison places the last Government promised, aiming to do so by 2031" (p.3) [2]. The 14,000 places due by 2031 that the Welland Oaks release presents as this government's "boom" are not a fresh target. They are the unbuilt balance of a pledge made three years before this government took office.

The same strategy discloses the price of finishing that pledge. "In 2021, the 20,000-place prison building programme was estimated to cost 5.2 billion pounds. Now, as this document reveals, the cost will be between 9.4 billion and 10.1 billion. The cost of this delay, therefore, could reach nearly 5 billion pounds" (p.2) [2]. The National Audit Office's independent assessment, published the same week, puts the same range at "at least 4.2 billion more than planned" (key facts, p.4) [3], and goes further on why: "HMPPS's expansion plan was unrealistic and was not prioritised by the government, with resulting delays that have exacerbated the current crisis" (para 19, p.11) [3]. Even on the revised 2031 timetable, the NAO's central scenario still shows "demand for spaces exceeding capacity by 12,400 places by the end of 2027" (para 19, p.11) [3].

None of this history, lineage or cost appears in the 13 November release. It presents 14,000 places by 2031 as a straightforward record rather than the tail end of a programme that has nearly doubled in cost and is still forecast short.

What the department's own newest statement says

The Ministry's second Annual Statement on Prison Capacity, presented to Parliament in January 2026, is the most recent official account of the same programme the Welland Oaks release credits with ending the crisis. It confirms the target has not moved: "based on the latest assessment of our delivery plans, the Government has maintained the existing target of 14,000 new places by 2031" (para 17, p.9) [4], and records "c.2,900" places delivered since July 2024 and "c.5,000" under construction by the end of 2025, including Welland Oaks (para 17, p.9) [4].

Two further admissions in that statement do not appear in the construction-progress release. First, the building programme does not close the gap on its own: "Without the Sentencing Act 2026 measures, demand is expected to exceed supply by June 2026 under the central scenario" (para 23, p.10) [4]. Supply only "keeps pace" with demand once a projected 7,500-place fall in the prison population, from early releases under the Sentencing Act 2026, is added to the modelling by February 2028 (para 7, p.7) [4]. Second, this programme is understood internally to be the last the department can easily deliver: "The Ministry of Justice currently does not own any parcels of land that would be suitable for new prisons beyond those already planned. No new land has been acquired in over 10 years, which has meant there are now no new uncommitted sites in our pipeline" (para 21, p.10) [4].

A release calling this "the largest prison building boom since the Victorian era" does not mention that, on the department's own figures, the boom only closes the capacity gap with help from early releases of existing prisoners, and that there is no further land in the pipeline once the current plan is finished.

The claims, tested

What the release says What the record shows Verdict
"The new prison forms part of the largest prison building boom since the Victorian era, as the Government delivers 14,000 additional places by 2031" [1] The government's own 10-Year Prison Capacity Strategy says this is "the 14,000 prison places the last Government promised" (p.3) [2], the unbuilt balance of a 20,000-place pledge made in October 2021 [3] The figure is real. It is a continuation of the prior government's target, not a new one.
"...after just 500 net places were added in the 14 years to July 2024" [1] True on the government's own account, but the same document shows the cost of finishing that 20,000-place programme has risen from an estimated 5.2 billion pounds in 2021 to 9.4 to 10.1 billion now (p.2) [2], and the NAO found the plan behind it "unrealistic and not prioritised" (p.11) [3] The release names the previous government's underbuilding but not the near-doubling in cost of finishing the job, or the watchdog's verdict on why.
The release frames the building programme as resolving the capacity crisis The department's own January 2026 Annual Statement says that without Sentencing Act 2026 early releases, "demand is expected to exceed supply by June 2026" (p.10) [4], and that the department "does not own any parcels of land... suitable for new prisons beyond those already planned" (p.10) [4] Building alone does not close the gap, and there is no further pipeline once this plan completes, on the department's own newest account.

Credit where due

The release's construction figures are specific and checkable: 269 million pounds spent, 85.5% of it within 50 miles of the site, 501 jobs created, 29 apprentices and 36 prison leavers upskilled [1]. The "3,300 places delivered" the minister cites lines up with, rather than contradicts, the department's own Annual Statement progression from around 2,900 delivered by the end of 2025 [4]. The 10-Year Prison Capacity Strategy is also unusually candid, in public, about its predecessor's record: it names the rise from 5.2 billion to 9.4 to 10.1 billion pounds in its own foreword rather than leaving it for others to find [2].

The mistakes, counted

A record presented without its lineage or its cost (1). The release's claim of "the largest prison building boom since the Victorian era" and "14,000 additional places by 2031" does not disclose that these are the unbuilt remainder of the 2021 pledge, whose cost has risen from an estimated 5.2 billion pounds to between 9.4 billion and 10.1 billion on the government's own figures, a rise the National Audit Office attributes partly to a plan it called "unrealistic and not prioritised by the government" [2] [3].

A boom that, by the department's own account, does not finish the job alone (2). The release does not mention that the government's own January 2026 Annual Statement says supply only keeps pace with demand once Sentencing Act 2026 early releases are added in, that without them "demand is expected to exceed supply by June 2026", or that the Ministry has acquired no new prison land in over 10 years and has "no new uncommitted sites in our pipeline" beyond the current plan [4].

Verdict

Four stars, from two documented mistakes. The construction at Welland Oaks is real, the spending figures hold up, and the government's own strategy document is candid about its predecessor's failures. What a press release calling this "the largest prison building boom since the Victorian era" does not tell readers is that the boom is finishing someone else's unmet pledge at close to double the original price, or that the department's own newest statement says the building programme only closes the capacity gap with help from early releases, and that there is no land for another one after this.

The star score counts two documented mistakes against the Ministry of Justice's 13 November 2026 press release on HMP Welland Oaks: it presents "14,000 additional places by 2031" as this government's building boom without disclosing that the department's own 10-Year Prison Capacity Strategy describes the figure as the unbuilt remainder of a 2021 pledge whose cost has risen from an estimated 5.2 billion pounds to 9.4 to 10.1 billion, a rise the National Audit Office partly attributes to a plan it called unrealistic; and it does not mention that the department's own January 2026 Annual Statement says the building programme alone will not keep pace with demand without Sentencing Act 2026 early releases, and that no new prison land has been acquired in over 10 years. Two falls in the 1 to 3 band: four stars; the bands are on the ratings page. This piece makes no finding about whether HMP Welland Oaks itself is being built safely, on time or on budget, only that the release omits the pledge's history, its near-doubled cost and the department's own account of what the building programme can and cannot do alone.

Sources

  1. New 1,700-place Leicestershire prison moves a step closer, Ministry of Justice, 13 November 2026
  2. 10-Year Prison Capacity Strategy, Ministry of Justice, December 2024
  3. Increasing the capacity of the prison estate to meet demand, National Audit Office, 4 December 2024
  4. Annual Statement on Prison Capacity: 2025, Ministry of Justice, January 2026